HOU Xiao-qing,DENG Lei,GAO Hai-ying,et al.Application of MBR Process in the Upgrading and Reconstruction Project of Shending River WastewaterTreatment Plant[J].China Water & Wastewater,2018,34(22):66-70.
MBR工藝在神定河污水處理廠升級改造工程中的應(yīng)用
- Title:
- Application of MBR Process in the Upgrading and Reconstruction Project of Shending River WastewaterTreatment Plant
- 文章編號:
- 1000-4602(2018)22-0066-05
分類號:- TU992.3
- 文獻(xiàn)標(biāo)志碼:
- C
- 摘要:
- 十堰神定河污水處理廠升級改造工程設(shè)計(jì)總規(guī)模為18×104 m3/d,其中一期工程仍沿用A/O+二沉池工藝,設(shè)計(jì)規(guī)模由原5.5×104 m3/d降負(fù)荷調(diào)整為4×104 m3/d,出水水質(zhì)需達(dá)到一級B排放標(biāo)準(zhǔn); 二期工程采用AAO+MBR工藝,設(shè)計(jì)規(guī)模由原11×104 m3/d擴(kuò)容到14×104 m3/d,出水水質(zhì)執(zhí)行一級A排放標(biāo)準(zhǔn)。兩期工程的混合出水水質(zhì)需達(dá)到一級A排放標(biāo)準(zhǔn)。投產(chǎn)運(yùn)行后,出水水質(zhì)優(yōu)于設(shè)計(jì)標(biāo)準(zhǔn)。
Abstract:- The design treatment capacity of the upgrading and reconstruction project of Shending River Wastewater Treatment Plant was 18×104 m3/d. In the first-stage project, A/O+ secondary sedimentation tank process was adopted and the treatment capacity was reduced from 5.5×104 m3/d to 4×104 m3/d. The effluent quality of the first-stage project was required to be better than the first class B discharge standard. The design capacity of second-stage project was increased from 11×104 m3/d to 14×104 m3/d, and AAO+MBR process was adopted as the treatment technology. The effluent quality of the second-stage project should meet the first class A discharge standard. The mixed effluent of the two projects should reach the first class A discharge standard. In the period of operation, the effluent quality was proven to be better than design discharge standard.
MBR工藝在神定河污水處理廠升級改造工程中的應(yīng)用 侯曉慶, 鄧 磊, 高海英, 曹明浩, 吳念鵬, 牛和昕(北京碧水源科技股份)
王領(lǐng)全中國給水排水2021-12-27
MBR工藝在神定河污水處理廠升級改造工程中的應(yīng)用
侯曉慶, 鄧 磊, 高海英, 曹明浩, 吳念鵬, 牛和昕
(北京碧水源科技股份有限公司, 北京 102206)
摘要:十堰神定河污水處理廠升級改造工程設(shè)計(jì)總規(guī)模為18×104 m3/d,其中一期工程仍沿用A/O+二沉池工藝,設(shè)計(jì)規(guī)模由原5.5×104 m3/d降負(fù)降調(diào)整為4×104 m3/d,出水水質(zhì)需達(dá)到一級B排放標(biāo)準(zhǔn); 二期工程采用AAO+MBR工藝,設(shè)計(jì)規(guī)模由原11×104 m3/d擴(kuò)容到14×104 m3/d,出水水質(zhì)執(zhí)行一級A排放標(biāo)準(zhǔn)。兩期工程的混合出水水質(zhì)需達(dá)到一級A排放標(biāo)準(zhǔn)。投產(chǎn)運(yùn)行后,出水水質(zhì)優(yōu)于設(shè)計(jì)標(biāo)準(zhǔn)。
The design treatment capacity of the upgrading and reconstruction project of Shending River Wastewater Treatment Plant was 18×104 m3/d. In the first-stage project, A/O+ secondary sedimentation tank process was adopted and the treatment capacity was reduced from 5.5×104 m3/d to 4×104 m3/d. The effluent quality of the first-stage project was required to be better than the first class B discharge standard. The design capacity of second-stage project was increased from 11×104 m3/d to 14×104 m3/d, and AAO+MBR process was adopted as the treatment technology. The effluent quality of the second-stage project should meet the first class A discharge standard. The mixed effluent of the two projects should reach the first class A discharge standard. In the period of operation, the effluent quality was proven to be better than design discharge standard.[1]侯曉慶,鄧 磊,高海英,等.MBR工藝在神定河污水處理廠升級改造工程中的應(yīng)用[J].中國給水排水,2018,34(22):66-70.
HOU Xiao-qing,DENG Lei,GAO Hai-ying,et al.Application of MBR Process in the Upgrading and Reconstruction Project of Shending River WastewaterTreatment Plant[J].China Water & Wastewater,2018,34(22):66-70.
參考文獻(xiàn)/References:
MBR工藝在神定河污水處理廠升級改造工程中的應(yīng)用
侯曉慶, 鄧 磊, 高海英, 曹明浩, 吳念鵬, 牛和昕
(北京碧水源科技股份有限公司, 北京 102206)
摘要:十堰神定河污水處理廠升級改造工程設(shè)計(jì)總規(guī)模為18×104 m3/d,其中一期工程仍沿用A/O+二沉池工藝,設(shè)計(jì)規(guī)模由原5.5×104 m3/d降負(fù)降調(diào)整為4×104 m3/d,出水水質(zhì)需達(dá)到一級B排放標(biāo)準(zhǔn); 二期工程采用AAO+MBR工藝,設(shè)計(jì)規(guī)模由原11×104 m3/d擴(kuò)容到14×104 m3/d,出水水質(zhì)執(zhí)行一級A排放標(biāo)準(zhǔn)。兩期工程的混合出水水質(zhì)需達(dá)到一級A排放標(biāo)準(zhǔn)。投產(chǎn)運(yùn)行后,出水水質(zhì)優(yōu)于設(shè)計(jì)標(biāo)準(zhǔn)。
The design treatment capacity of the upgrading and reconstruction project of Shending River Wastewater Treatment Plant was 18×104 m3/d. In the first-stage project, A/O+ secondary sedimentation tank process was adopted and the treatment capacity was reduced from 5.5×104 m3/d to 4×104 m3/d. The effluent quality of the first-stage project was required to be better than the first class B discharge standard. The design capacity of second-stage project was increased from 11×104 m3/d to 14×104 m3/d, and AAO+MBR process was adopted as the treatment technology. The effluent quality of the second-stage project should meet the first class A discharge standard. The mixed effluent of the two projects should reach the first class A discharge standard. In the period of operation, the effluent quality was proven to be better than design discharge standard.[1]侯曉慶,鄧 磊,高海英,等.MBR工藝在神定河污水處理廠升級改造工程中的應(yīng)用[J].中國給水排水,2018,34(22):66-70.
HOU Xiao-qing,DENG Lei,GAO Hai-ying,et al.Application of MBR Process in the Upgrading and Reconstruction Project of Shending River WastewaterTreatment Plant[J].China Water & Wastewater,2018,34(22):66-70.
[1] 吳媛媛,張彩云,曹明浩,等. 神定河污水處理廠提標(biāo)改造——CAS-MBR復(fù)合工藝[J]. 凈水技術(shù),2016,35(4):11-15,87. Wu Yuanyuan,Zhang Caiyun,Cao Minghao,et al. Upgrading and reconstruction of Shendinghe WWTP in application of combined process of CAS-MBR[J]. Water Purification Technology,2016,35(4):11-15,87(in Chinese).
相似文獻(xiàn)/References:
[1]王 亮.馬來西亞Pantai地埋式污水廠環(huán)網(wǎng)供配電結(jié)構(gòu)設(shè)計(jì)[J].中國給水排水,2018,34(22):63.
WANG Liang.Power Supply and Distribution Structure Design of Ring Network for Pantai Underground Wastewater Treatment Plantin Malaysia[J].China Water & Wastewater,2018,34(22):63.
[2]邱明海.北京市垡頭污水處理廠改擴(kuò)建工程設(shè)計(jì)技術(shù)方案[J].中國給水排水,2018,34(20):13.
QIU Ming hai.Reconstruction and Expansion Design Technical Plan of Beijing Fatou Wastewater Treatment Plant[J].China Water & Wastewater,2018,34(22):13.
[3]郝二成,郭毅,劉偉巖,等.基于數(shù)學(xué)模擬的污水廠運(yùn)行分析——建模與體檢[J].中國給水排水,2020,36(15):23.
HAO Er-cheng,GUO Yi,LIU Wei-yan,et al.Operation Analysis of Wastewater Treatment Plant Based on Mathematical Simulation: Modeling and Examination[J].China Water & Wastewater,2020,36(22):23.
[4]張?jiān)?王陽,張宏偉,等.陽泉市污水處理二期工程BARDENPHO工藝設(shè)計(jì)和運(yùn)行[J].中國給水排水,2020,36(16):64.
ZHANG Yue,WANG Yang,ZHANG Hong-wei,et al.Design and Operation of BARDENPHO Process in Phase Ⅱ Project of Yangquan Wastewater Treatment Plant[J].China Water & Wastewater,2020,36(22):64.
[5]祝新軍,蔡芝斌,姚斌,等.紹興污水處理廠氣浮設(shè)備的優(yōu)化改造[J].中國給水排水,2020,36(16):101.
ZHU Xin-jun,CAI Zhi-bin,YAO Bin,et al.Optimization and Modification of Air Floatation Equipment in Shaoxing Wastewater Treatment Plant[J].China Water & Wastewater,2020,36(22):101.
[6]王文明,楊淇椋,蔡依廷,等.MSBR工藝在高排放標(biāo)準(zhǔn)污水處理廠的應(yīng)用[J].中國給水排水,2020,36(16):111.
WANG Wen-ming,YANG Qi-liang,CAI Yi-ting,et al.Application of MSBR Process in Wastewater Treatment Plant with Stringent Discharge Standard[J].China Water & Wastewater,2020,36(22):111.
[7]郝二成,郭毅,劉偉巖,等.基于數(shù)學(xué)模擬的污水廠運(yùn)行分析——控制與優(yōu)化[J].中國給水排水,2020,36(17):23.
HAO Er-cheng,GUO Yi,LIU Wei-yan,et al.Operation Analysis of Wastewater Treatment Plant Based on Mathematical Simulation: Control and Optimization[J].China Water & Wastewater,2020,36(22):23.
[8]王陽,張?jiān)?王曉康,等.高排放標(biāo)準(zhǔn)下的改良AAO+深度處理工程案例[J].中國給水排水,2020,36(18):56.
WANG Yang,ZHANG Yue,WANG Xiao-kang,et al.Project Case of Modified AAO and Advanced Treatment Process under High Emission Standards[J].China Water & Wastewater,2020,36(22):56.
[9]鄭楓,慕楊,孫遜.MBR工藝用于山東省某污水處理廠擴(kuò)建工程[J].中國給水排水,2020,36(18):81.
ZHENG Feng,MU Yang,SUN Xun.MBR Process Used in Expansion Project of a Sewage Treatment Plant in Shandong Province[J].China Water & Wastewater,2020,36(22):81.
[10]張莉,余國富,瞿露,等.重慶市某污水處理廠一級A提標(biāo)改造運(yùn)行效果分析[J].中國給水排水,2020,36(18):95.
ZHANG Li,YU Guo-fu,QU Lu,et al.Analysis on the Operation Effect of a WWTP Upgrading Project for the Firstlevel A Standard in Chongqing[J].China Water & Wastewater,2020,36(22):95.
備注/Memo
作者簡介:侯曉慶(1981- ), 女, 陜西三原人, 本科, 工程師, 主要從事膜工藝設(shè)計(jì)等相關(guān)工作。 E-mail:houxiaoqing@originwater.com
收稿日期:2018-05-04
近期發(fā)表